  1. From the ‘Explorer’ tab, right click on your project or package and select ‘Manage Baselines’.
  2. The Baseline screen will open.   Click on ‘Create’ from the toolbar.
  3. The Create Baseline screen will open. Add the Name and Description details in the appropriate fields provided and click ‘Continue’.
  4. The Baseline has been created and will be visible in your Baseline list view.

...

  1. From the ‘Explorer’ tab, right click on the project or package you would like to restore a baseline for.
  2. Click on ‘Manage Baselines’ to open the Baseline screen.
  3. Click to select the baseline you would like to delete.
  4. Click on the ‘Delete’ button on the toolbar. A confirmation message will appear.   To proceed, click ‘OK’.

Restoring a Baseline

...

  1. From the ‘Explorer’ tab, right click on the project or package you would like to restore a baseline for.
  2. Click on ‘Manage Baselines’ to open the Baseline screen.
  3. Click to select the baseline you would like to revert back to.
  4. Click on the ‘Restore’ button on the toolbar. A confirmation message will appear.   To proceed, click ‘OK’.
  5. When the baseline has been successfully restored, the following message will appear: