Bulk Update Test Script Status

You can quickly update multiple test scripts to either a status of ‘In Progress’ or ‘Passed’, by doing a bulk update. To do this:

  1. Expand the execution set to the package or plan containing the test scripts.
  2. Double click the package/plan or right click and select view/edit package/plan. The test execution scripts in the plan will be displayed.
  3. Select the tests by clicking the box on the left hand side - you can select all by selecting the top one.
  4. Select the status from the pick list at the top and then click on ‘Bulk Update’.

The selected scripts will now be updated to the selected status.

Bulk Update Test Script Assignments

You can quickly assign multiple test scripts to any user by performing a bulk update. To do this:

  1. Expand the execution set to the package or plan containing the test scripts.
  2. Double click the package/plan or right click and select view/edit package/plan.

    The test execution scripts in the plan will be displayed.
  3. Select the tests by clicking the box on the left hand side - you can select all by selecting the top one.
  4. Select the user from the pick list at the top and then click on ‘Assign Scripts’.

The selected scripts will now be updated to the selected user.

Bulk Copy

You can quickly copy Execution Set Scripts by doing a bulk update. To do this:

  1. Expand the package or plan containing the Execution Sets.
  2. Double click the package/plan or right click and select view/edit package/plan.

    The Execution Set Scripts will be displayed.

  3. Select the items by clicking the box on the left hand side - you can select all by selecting the top one.
  4. Click the Copy button at the top  OR  click the split arrow next to Copy, tick Retain Structure and then Copy.

    Retain Structure will retain any package structure being copied.

  5. A pop up window is displayed, select the “To” package where you would like to Copy the items to.
  6. Click OK; the selected items will now be copied to the selected position.

Bulk Move

You can quickly move Execution Set Scripts by doing a bulk update. To do this:

  1. Expand the package or plan containing the Execution Sets.
  2. Double click the package/plan or right click and select view/edit package/plan.

    The Execution Set Scripts will be displayed.
  3. Select the items by clicking the box on the left hand side - you can select all by selecting the top one.
  4. Click the Move button at the top  OR  click the split arrow next to Move, tick Remove Empty Package and/or Retain Structure and then Move.

    'Remove Empty Package' will remove an empty package from the “From” package that is being moved and 'Retain Structure' will retain any package structure being moved.

  5. A pop up window is displayed, select the “To” package where you would like to Move the items to.
  6. Click OK, the selected items will now be moved to the selected position.